Case Study: PNB 118
0m
Project: PNB118
Owner: PNB
Builder: RSP
Location: Malaysia, KL
P2
How we do ...
Fixture Installation

Combine with curtain wall drawing make the product operation manual provide to the cutain wall factory for references

Outlet Of The Fixture Wire

According to the curtain wall node drawing to outlet wire and cut out hole.
Ensure that the curtain wall cut out plan does not damage the overall structure to ensure the safety of curtain wall panels

Safety Provisions
  1. Waterproof
  2. Fireproof
  3. Anti-leakage
P3
How we do ...
Case Study: PNB 118
  1. Before the fixture is installed, the connector must be tightened in place
  2. Place the recessed part of the curtain wall, and the top bracket of the fixture must correspond to the pre-fixed bracket of the curtain wall.
  3. The fixture is pulled down about 10mm and the corresponding screws on the pre-fixed bracket of the lower curtain wall are raised at the same time, so that the lower bracket of the fixture is accurately inserted into the pre-fixed bracket, and then locked the screws.
Fixture Installation Node
Outlet Wire Node
Custom Made Node
Projects
P4
How we do ...
Case Study: PNB 118
Projects
P5
How we do ...
Case Study: PNB 118
Electromechanical and Production Specifications
  1. Electromechanical equipment certification standards, all pipelines, switching power supplies and lighting equipments meet the corresponding certification standards.It is also meet the requirements of the project submission for review. PNB118 uses the standard of the Malaysian local government——the SIRIM standard.
  2. Regarding coordination of electrical systems and other cooperating companys of the project, fire protection, ventilation, elevators.
  3. The final result will be show in the BIM system
Projects
P6
How we do ...
Case Study: PNB 118
Electromechanical Installation BIM System
  1. Deepened electromechanical drawings as concept drawings.
  2. Find problems through concept drawings through BIM system and solve them
  3. ISD drawings were exported by BIM as project construction drawings. ISD drawings can more accurately reflect the relationship between the actual dimensions and the relevant units.
Projects
P7
How we do ...
Case Study: PNB 118
Projects
P8
How we do ...
Case Study: PNB 118
Fixture Quality Control
  1. There are strict testing standards before the production of fixtures
  2. Strict quality control system in the production process of fixtures
  1. Curtain wall integrated with luminaire approach inspection and test plan.
  1. Incoming inspection of curtain wall
Projects
P9
How we do ...
Case Study: PNB 118
Site Construction Management
  1. Worker training and entry time
  2. Ordering cycle of construction materials
  3. Determining the pipeline construction steps and construction time according to the construction progress of the curtain wall and indoor
  4. The installation time of the distribution box and control equipments under the conditions that the high and low voltage rooms meet the construction conditions
  5. Divisional and overall commissioning time
Projects
P9
How we do ...
Case Study: PNB 118
  1. Safety for all relevant products
  2. To ensure the consistency and stability of all the fixture operation due to long construction period
  3. Products quality guarantee for this major project